Livestock building

Pig farm with the whole roof lined

The whole warehouse roof insulated from the inside, fitted from scaffolding.

Benavente (Zamora)
Roofs
Refurbishment
Worker fitting reflective insulation under the roof from scaffolding
Warehouse with the roof lined with reflective insulation
Inside the warehouse with the roof already insulated
Side view of the insulated roof

What was needed

A working building with a bare metal roof: very hot in summer and cold in winter for the animals.

What was done

Reflective insulation under the sheeting, from one end of the building to the other, with joints sealed with tape.

How it was installed

  1. The building is set out and it is decided whether the membrane goes under the purlins or between the sheeting and the purlins, depending on new build or refurbishment.
  2. The roll is run from one side of the building to the other, from scaffolding or a platform, and fixed to the structure.
  3. Joints between rolls are overlapped and sealed with aluminium tape so the surface is continuous.
  4. The planned air gap is kept and junctions with walls, windows and openings are finished off.

Guidance installation for roofs. Ask us if you want more detail.